Indian Government constantly reviews the security environment and decides about induction of appropriate defence equipment/platforms, including various kinds of ships/submarines for the Navy.
Major warship construction projects of the Indian Navy running behind schedule include Project-15A (P-15A) and Project-17 (P17). The cost escalation in these two projects has been about 225% and 260% respectively.
The major cost escalation & delay has been due to uncertainties associated with the complex warship building process. Reasons for delay and cost escalations in respect of P-15A and P-17 are as follows: